Skip to content
RCTSHUMAFABRICATION
IndustrialAlberton, Gauteng

Alrode Distribution Warehouse

Full portal frame structure and mezzanine platform for a 9,000 m² logistics warehouse, fabricated and erected in 11 weeks.

40 m
Clear span
S355JR
Steel grade
310 t
Total tonnage
11 weeks, fabrication to erection
Programme
01

The Spec

The client needed a clear-span 40 m warehouse with a 1,800 m² mezzanine office platform, on a fabrication and erection programme compressed to fit around a fixed lease start date.

02

Our Approach

We ran detailing, procurement, and fabrication in parallel — cutting foundation-critical base plates first while beam and truss fabrication continued — and pre-planned the erection sequence to run two crane crews simultaneously on opposite ends of the frame.

03

The Result

Steel was delivered piece-marked to the erection sequence with zero site rework, and the frame was standing four days ahead of the compressed programme, allowing cladding contractors to start early.

[SPC]Details

Project Specification

Clear span40 m
Steel gradeS355JR
Total tonnage310 t
Programme11 weeks, fabrication to erection
Next Step

Have a similar project in mind?

Send us the details and we'll scope it the same way — spec, solution, and a firm quote.